How do you calculate economic order quantity (EOQ)?

Short answer

EOQ is the square root of (2 × annual demand × cost per order ÷ annual holding cost per unit). Holding cost per unit is the unit cost times the holding rate. Order that quantity each time to minimize the sum of ordering and holding costs. Add safety stock to the reorder point to cover demand during the lead time.

The economic order quantity balances two costs that move in opposite directions: ordering more often costs more in orders, and ordering in larger lots costs more to hold. EOQ is the lot size where the two annual costs are equal.

What is the EOQ formula?

  • Holding cost per unit per year, H = unit cost × holding cost rate.
  • EOQ = √(2 × D × S ÷ H), where D is annual demand and S is the cost of placing one order.
  • Orders per year = D ÷ EOQ.

What does a worked example look like?

Annual demand is 12,000 units, each order costs 50, a unit costs 8 and holding costs 25% of unit cost a year.

  • H = 8 × 0.25 = 2.00 per unit per year.
  • EOQ = √(2 × 12,000 × 50 ÷ 2.00) = √600,000 = 774.6, rounded to 775 units.
  • Orders per year = 12,000 ÷ 775 = 15.5.
  • Annual ordering cost = 15.5 × 50 = 774; annual holding cost = 775 ÷ 2 × 2.00 = 775.

At the optimum the two costs are almost equal, and the total of about 1,549 is the lowest the model can reach. The purchase cost of the units is not included.

How do safety stock and the reorder point work?

Safety stock covers demand variation during the lead time: z × the standard deviation of daily demand × √lead time, rounded up. The reorder point is average daily demand × lead time + safety stock.

With 250 working days, daily demand is 48 units. For a 6-day lead time, a daily standard deviation of 12 units and a 95% service level (z = 1.645), safety stock = 1.645 × 12 × √6 = 48.4, rounded up to 49. The reorder point is 48 × 6 + 49 = 337 units.

What does EOQ assume?

Constant demand, a fixed cost per order, no quantity discounts and instant replenishment at the reorder point. The safety stock formula adds the assumption that daily demand is roughly normal and independent from day to day, and that the lead time is fixed. If those do not hold, treat the result as a starting point.

The EOQ, safety stock and reorder point calculator does this for each SKU and adds the annual ordering and holding costs.