Template · Management

Earned value management (EVM) project tracker

Track a project's schedule and cost with planned value, earned value, SPI, CPI and an estimate at completion.

See download membership

Preview below without an account. Downloads require the $19.85 yearly membership. Already registered? Sign in. XLSX, ODS and XML keep formulas; CSV and Numbers contain values only.

XLSXCSVODSXMLNumbers
Earned value management (EVM) project tracker
Example data — replace the blue input cells with your own.
Headline resultsSPICPIEACVAC
0.900.93$2,925,416-$193,416
Inputs
ProjectExample warehouse automation
Status dateJan 31, 2027Planned value is measured at this date
Schedule and cost tolerance (plus or minus)5%SPI and CPI inside this band from 1.00 read as on schedule or on budget
Project start (earliest planned start)Oct 1, 2026
Project totals (USD)
Budget at completion (BAC)$2,732,000
Planned value (PV)$1,189,640BAC x planned % at the status date
Earned value (EV)$1,073,500BAC x % complete

Showing the first 16 of 49 rows and 5 of 5 columns. Cells with formulas show the formula on hover.

What does this template do?

This workbook tracks a project's cost and schedule performance with earned value management (EVM). It is for project managers, controls analysts and anyone who reports project status to a sponsor. Enter a budget at completion, planned dates, percent complete and actual cost for each work package, then set the status date.

The Work packages tab calculates planned value (budget multiplied by the planned share at the status date, which rises in a straight line over the planned days), earned value (budget multiplied by percent complete) and the schedule and cost variances. The Dashboard turns these into SPI, CPI, the estimate at completion, the variance at completion and the to-complete performance index. It also gives a status line for schedule and cost and a 12-month planned S-curve.

The example is a fictional warehouse automation project with twelve work packages and a total budget of about $2.7 million. Replace the blue cells with your own work breakdown structure.

What’s inside

  • Planned value from straight-line phasing between each work package's planned start and finish
  • SPI, CPI, estimate at completion and variance at completion on the Dashboard
  • Schedule and cost status lines with a tolerance band that you set
  • Planned S-curve for 12 months from the project start, built from the work package rows
  • Room for 60 work packages; spare rows stay blank

Which tabs does the workbook have?

TabWhat it holds
DashboardStatus date, headline SPI, CPI, EAC and VAC, project totals, status lines and the monthly planned S-curve.
Work packagesOne row per work package: budget, dates, percent complete, actual cost and the earned value calculations.
NotesPurpose, steps, formulas used, assumptions and limits.

What formulas does this template use?

This template holds 1,110 formulas in 1,329 cells across 3 tabs, so 84% of its cells calculate. They use 7 distinct functions; the longest formula is 175 characters and 91 of them read from another tab.

FunctionUsesWhat it does
IF2,609one result when a test is true, another when false
SUM34adds numbers
EOMONTH12last day of a month, months later
COUNTIF2counts cells meeting one condition
ABS1absolute value
MIN1smallest value
SUMPRODUCT1multiplies matching entries, then adds them

Counted from the workbook itself. Only functions that Excel, LibreOffice Calc, Google Sheets and Apple Numbers evaluate the same way are used, so the formulas survive every download format.

How do you use it?

  1. On the Dashboard, enter the project name, the status date and the tolerance.
  2. On the Work packages tab, enter each WBS code, name, owner, budget, planned dates, percent complete and actual cost.
  3. Read SPI, CPI, EAC and VAC in the tiles at the top of the Dashboard.
  4. Check the schedule and cost status lines and the to-complete performance index.
  5. Compare the monthly planned-value table with actual progress at each review.

What is it good for?

  • Monthly project status report to a steering group
  • Forecasting the final cost of a fixed-scope project
  • Checking a contractor's schedule and cost claims against plan
  • Teaching earned value terms to a project team

Questions about this sheet

What does SPI tell me?

SPI is earned value divided by planned value. Above 1 means more work is done than planned at the status date, and below 1 means the project is behind schedule. The status line uses the tolerance you set.

Why is CPI blank?

CPI is earned value divided by actual cost. It stays blank until some actual cost is entered, so the workbook never divides by zero.

How is the estimate at completion calculated?

EAC equals budget at completion divided by CPI. It assumes the cost performance so far continues to the end of the project.

Does the sheet measure percent complete?

No. Percent complete is an input. Enter it from your own measurement of the work done.