A 42-circuit 208Y/120 V panel schedule with phase totals, NEC 220.44 receptacle demand and current.

See download membership

Preview below without an account. Downloads require the $19.85 yearly membership. Already registered? Sign in. XLSX, ODS and XML keep formulas; CSV and Numbers contain values only.

XLSXCSVODSXMLNumbers
Electrical panel load schedule
Example data — replace the blue input cells with your own.
CircuitDescriptionLoad typePolesPhaseConnected load (VA)Demand load (VA)Phase A (VA)Phase B (VA)Phase C (VA)Breaker (A)
1Lighting, corridor northLighting1C1,4401,440001,44020
2Lighting, corridor southLighting1A1,4401,4401,4400020
3Lighting, open officeLighting1C2,6402,640002,64020
4Lighting, classroomsLighting1A2,8802,8802,8800020
5Lighting, libraryLighting1B2,1602,16002,160020
6Lighting, gymnasiumLighting1B3,3603,36003,360020
7Lighting, kitchenLighting1C1,2001,200001,20020
8Lighting, officesLighting1A1,9201,9201,9200020
9Lighting, exterior and car parkLighting1C1,8001,800001,80020
10Lighting, stairs and lobbyLighting1A1,3201,3201,3200020
11Receptacles, lobbyReceptacle1C1,9201,248001,24820
12Receptacles, receptionReceptacle1B1,4409360936020

Showing the first 16 of 49 rows and 11 of 11 columns. Cells with formulas show the formula on hover.

What does this template do?

This schedule lists 42 circuits on a 208Y/120 V, three-phase, four-wire panel and checks the connected load against the main breaker. Each circuit has a description, load type, number of poles, phase, connected load and breaker size. The example panel is fictional and carries lighting, receptacle, HVAC and equipment loads.

The Summary tab applies the NEC 220.44 receptacle demand: the first 10 kVA of connected receptacle load at 100% and the remainder at 50%. The demand is spread across the receptacle circuits in proportion to their connected load. Single-pole circuits sit on one phase, two-pole circuits split evenly across two phases, and three-pole circuits split across all three.

The sheet totals each phase, reports the largest deviation from the average as the phase imbalance, and calculates the total current as kVA × 1000 ÷ (√3 × 208 V). Every result is labelled as a value to verify. The workbook adds up loads; it does not size conductors, breakers or feeders.

What’s inside

  • 42 circuits, each with load type, poles, phase, connected load and breaker size
  • NEC 220.44 receptacle demand: first 10 kVA at 100%, remainder at 50%, applied to each receptacle circuit
  • Phase totals from pole count: single-pole on one phase, two-pole on AB, BC or CA, three-pole on ABC
  • Imbalance = largest deviation from the average phase ÷ the average
  • Total amps = kVA × 1000 ÷ (√3 × 208), compared with the main breaker rating

Which tabs does the workbook have?

TabWhat it holds
ScheduleCircuit list with description, load type, poles, phase, connected load, demand, phase split and breaker size.
SummaryPanel settings, receptacle demand, load by type, phase balance, total kVA and current, and checks.
NotesWhat the workbook does, how to use it, the demand and phase method, the limits and the professional-verification note.

What formulas does this template use?

This template holds 213 formulas in 604 cells across 3 tabs, so 35% of its cells calculate. They use 9 distinct functions; the longest formula is 82 characters and 62 of them read from another tab.

FunctionUsesWhat it does
IF555one result when a test is true, another when false
OR126true when any test is true
SUM15adds numbers
SUMIF13adds values meeting one condition
ABS5absolute value
MAX2largest value
COUNT1counts numeric cells
MIN1smallest value
SQRT1square root

Counted from the workbook itself. Only functions that Excel, LibreOffice Calc, Google Sheets and Apple Numbers evaluate the same way are used, so the formulas survive every download format.

How do you use it?

  1. On the Summary tab, enter the panel name, the voltage and the main breaker rating.
  2. On the Schedule tab, replace the example circuits with your own, one row per circuit.
  3. Choose the load type, poles and phase for each circuit from the drop-down lists.
  4. Read the receptacle demand, phase totals and imbalance on the Summary tab.
  5. Check the total current against the main breaker and confirm the check cells say OK.

What is it good for?

  • Preparing a first load schedule for a commercial or institutional panel
  • Checking phase balance before a panel is wired
  • Testing how the NEC 220.44 receptacle demand changes the total
  • Teaching how loads are split across three phases

Questions about this sheet

Does the sheet size breakers and conductors?

No. It adds up loads and shows the current. Conductor sizing, breaker coordination, voltage drop and feeder design need a separate calculation by a licensed engineer.

Why is the receptacle demand lower than the connected load?

NEC 220.44 allows the first 10 kVA of connected receptacle load at full value and half of the remainder. The reduction is shown on the Summary tab.

How are two-pole and three-pole circuits counted by phase?

A two-pole circuit on AB adds half its demand to phase A and half to phase B. A three-pole circuit adds a third of its demand to each phase.

Can I use the results on a permit submission?

Not as they stand. Confirm the calculation against the adopted NEC edition and local amendments, and have a licensed electrical engineer check it first.